Why Is Nepal Canceling Hundreds of Infrastructure Contracts?

Why Is Nepal Canceling Hundreds of Infrastructure Contracts?

Director Shubhanjan Dahal of the Department of Roads emphasizes that these mass cancellations are the result of a rigorous multi-year study into contractor accountability and performance. The infrastructure landscape in Nepal is witnessing a radical transformation as the government attempts to dismantle a culture of systemic delay that has plagued the nation for years. For decades, the “sick contract” syndrome has left vital arteries of the country—from critical bridges in the Terai to strategic highways in the Himalayas—in a state of permanent construction. Contractors often secured these projects by underbidding or leveraging political connections, only to divert mobilization advances into unrelated business ventures, essentially holding public development hostage. By 2026, the Department of Roads has reached a breaking point, resulting in the termination of 172 major contracts to prevent further hemorrhaging of the state treasury. This aggressive purge signals a paradigm shift in administrative tolerance, moving away from a history of endless time extensions and toward a rigid framework of accountability that prioritizes national progress over contractor convenience.

The Spectrum: Long-Term Delays and Hostage Projects

The projects currently under the scanner represent a wide range of failure, with some contracts remaining active for over fifteen years despite achieving negligible progress. In the Kathmandu Valley and its surrounding districts, essential roadworks such as the Samakhusi-Gongabu and Sitapaila-Ramkot expansions have languished since the early 2010s, with completion rates hovering between 13 and 25 percent. These stalled sites have created significant health and safety hazards, with dust pollution and unpaved surfaces affecting thousands of daily commuters. The government’s decision to finally pull the plug on these agreements reflects a realization that the original contractors had no intention or capacity to finish the work, regardless of how many warnings were issued. This chronic delay has not only stunted local economic growth but also eroded public trust in the state’s ability to manage its most basic infrastructure needs efficiently and transparently.

Conversely, some of the most controversial cancellations involve infrastructure that is tantalizingly close to completion, with physical progress reaching between 91 and 95 percent. Projects like the Sun Koshi Phoksingtar Bridge and the four-lane Mahakali River Bridge have become symbols of a different type of contractor negligence. In these cases, builders often halted work on the final five percent of the project to use it as a bargaining chip for cost escalations or additional funding, knowing the government would be desperate to open the facility. By terminating these nearly finished projects, the Department of Roads is taking a high-stakes gamble to end the practice of financial “blackmail.” While this leaves the public unable to use almost-completed bridges and roads in the short term, officials argue it is a necessary deterrent to prevent future contractors from adopting similar predatory tactics during the final stages of high-value national pride corridors.

Economic Implications: The High Cost of Starting Over

Terminating a contract is rarely a clean break; it often triggers a cascade of financial challenges that place a massive burden on the national budget. When a “sick” contract is canceled, the remaining work must be re-evaluated and put back out to tender at current market rates, which are frequently double or triple the original bid prices due to inflation and the cost of mobilizing a new workforce. For example, the Paudi-Sundarbazar road project in Lamjung illustrates this fiscal nightmare; after paying out substantial sums for partial work, the government found that completing the final 29 percent of the road would now cost over 1.1 billion rupees—a staggering increase from the original total contract value. This discrepancy forces the state to divert funds from other potential development projects just to fix the mistakes of the past, creating a cycle of budgetary strain that complicates long-term financial planning across all ministries.

In an attempt to mitigate these losses, the Department of Roads has launched aggressive recovery processes to reclaim government dues from non-performing firms. Legal mechanisms are being utilized to freeze bank guarantees and recover mobilization advances that were never translated into physical work on the ground. A prominent case involves the Mangalsen-Suvakh nad strategic road, where the state is seeking to claw back nearly 382.4 million rupees. However, the path to actual financial recovery is riddled with bureaucratic and legal obstacles that often favor the contractor. Despite clear evidence of negligence, the process of liquidating assets and returning funds to the treasury is slow and inconsistent, often resulting in prolonged litigation that costs the state even more in legal fees and administrative overhead. This struggle highlights the urgent need for more robust procurement laws that protect public funds from the moment a contract is signed.

Legal Gridlock: The Role of Judicial Intervention

One of the most significant barriers to cleaning up the infrastructure sector has been the frequent intervention of the court system, which often grants interim orders to contractors whose agreements have been terminated. These stay orders effectively freeze a project in its current state, preventing the government from bringing in a new contractor to finish the work. This legal maneuvering allows negligent firms to maintain a stranglehold on public projects even after their failure has been officially documented. In Lalitpur, for instance, six major infrastructure packages were canceled due to extreme negligence, yet the Patan High Court issued interim orders for all of them shortly thereafter. This judicial interference creates a state of indefinite limbo where the government is legally barred from taking action, and the public is left to deal with the consequences of unfinished, often dangerous, construction sites.

This pattern of legal gridlock suggests a deeper disconnect between administrative goals and judicial interpretations of contract law. While the Department of Roads views termination as a vital tool for public accountability, contractors successfully argue that their right to due process has been violated or that the government contributed to the delays. The resulting court battles can drag on for years, during which time the half-finished infrastructure continues to deteriorate, leading to even higher repair and completion costs once the legal issues are finally resolved. To address this, there is a growing call among policy experts for the establishment of specialized fast-track courts or arbitration panels dedicated to infrastructure disputes. Such a system would ensure that legal disagreements do not lead to the total paralysis of national development goals, allowing projects to proceed while financial or procedural disputes are settled in parallel.

Divided Perspectives: Bureaucracy Versus Industry

The mass cancellation of contracts has exposed a sharp divide in how different stakeholders view the causes of project failure. Government officials maintain that the purge is a move of last resort against contractors who treat mobilization funds like personal loans. However, public procurement experts argue that the state itself is often a primary contributor to “sick” contracts. Analysts point out that the government frequently fails to provide necessary site clearances, environmental permits, and timely payments before a project begins. When a project sits for over a decade without progress, it is often a failure of bureaucratic oversight just as much as it is contractor incompetence. From this perspective, canceling a contract after fourteen years of inactivity is an admission of systemic failure across the entire project lifecycle, suggesting that accountability must be shared between the private sector and the public administration.

From the construction industry’s viewpoint, the government’s aggressive policy is often dismissed as a “stunt” for political popularity rather than a genuine attempt at reform. Industry leaders claim that contractors are being used as convenient scapegoats for deeper structural issues within the ministries. They cite examples where technical designs remained unapproved for four years, making it impossible for construction to start despite the contractor’s willingness. Builders argue that the focus should be on solving these bureaucratic bottlenecks and fostering a collaborative environment rather than resorting to punitive measures that bankrupt local companies. They contend that terminating projects that are nearly finished is a waste of state resources and that a more balanced approach—one that addresses funding gaps and design approvals—would be far more effective in delivering functional infrastructure.

Strategic Evolution: Reforming the Procurement Lifecycle

As Nepal moved beyond the initial shock of these mass cancellations, the focus shifted toward creating a more resilient and transparent procurement framework. The Department of Roads implemented stricter pre-qualification criteria to ensure that only firms with proven technical and financial capacity could bid on high-stakes projects. This included a more rigorous vetting of a contractor’s current workload to prevent “over-stretching,” where a single firm manages more projects than it can realistically handle. Furthermore, authorities placed a new emphasis on ensuring that all land acquisition and environmental clearances were finalized before any contract was even advertised. By removing these common excuses for delay at the outset, the government sought to create a landscape where failure could be more clearly attributed to contractor performance rather than bureaucratic hurdles, effectively stabilizing the industry.

The ultimate success of this infrastructure cleanup was determined by how effectively the state balanced punitive actions with structural incentives for performance. Stakeholders recognized the need for “performance-based” contracting models, where payments were more closely tied to the achievement of specific milestones rather than simple time-based mobilization. Additionally, the integration of digital project monitoring tools allowed for real-time tracking of construction progress, providing an early warning system for projects at risk of becoming “sick.” By 2026, these reforms had begun to create a more disciplined construction sector, though the financial scars of previous failures remained a significant burden. This evolution offered a blueprint for other developing nations, demonstrating that systemic change requires a total overhaul of the relationship between the state and the private sector to ensure national development goals are met.

Subscribe to our weekly news digest.

Join now and become a part of our fast-growing community.

Invalid Email Address
Thanks for Subscribing!
We'll be sending you our best soon!
Something went wrong, please try again later